PUPR Ministry
Ongoing
Indonesia
PUPR Ministry
21 October 2021 - 21 October 2026
Detail Engineering Design (DED), Project Supervision
Project Name
Implementation Consultant SPAM Regional Wosusokas Water Supply System
Country
Location
Indonesia
Clients
PUPR Ministry
Association
HYDEA S.p.A (https://www.hydea.it/en/) and SWS Consulting Engineering (https://swsconsulting.it/), Italy
Duration of Assignment
N/A
Start Date
21 October 2021
Completion Date
21 October 2026
Approx. Value of the Contract
N/A
The activities of the Wosusokas Regional SPAM IC consist of the activities of :
a. Stage I : Detailed Engineering Design and Tender Documents: 1) Inception phase; 2) Review of Existing Detailed Engineering Design; 3) Preparation of Tender/Bidding Documents for Procurement of Works and Goods; 4) Review and Facilitate the Construction Permits
b. Stage II : Assistance during Tendering: 1) Tender process; 2) Bid Evaluation Process; 3) Contract Negotiation; 4) Award:
c. Stage III : Supervision of Construction Works and Supplies
d. Stage IV : Assistance during Defects Notification Period and Closure of Project.
The activity of stage IV will be carried out after project handing over from the Contractors to CMO.